China Merchants Port Holdings, the Sri Lanka Ports Authority and Access Engineering PLC have agreed to abandon the South Asia Commercial and Logistics Hub in the Port of Colombo, a project announced three and a half years ago as the largest commercial and logistics complex in South Asia.

Under a settlement agreement signed by the three partners, the Daily FT reported, the shareholders will recover about $29.8 million of the $37.1 million they had put into the project company in cash. The agreement ends the Shareholders Agreement, the Build-Operate-Transfer Agreement and the Site Lease Agreement early, and settles all matters relating to the project with immediate effect.

The Sunday Times, reporting from the announcement filed with the Hong Kong Stock Exchange, puts the Ports Authority’s own obligation at $21.905 million, payable to the project company as a lump sum within 30 days of the settlement.

Four numbers, and what each one measures

The figures reported across the two accounts are not competing claims. They measure different things, and they reconcile.

FigureWhat it is
$392 millionThe investment announced when the agreements were signed, reported by the Daily FT in April 2023
$37.1 millionWhat the shareholders actually contributed in cash, per the project company’s audited accounts to 31 December 2025
$29.8 millionWhat they get back under the settlement
$21.905 millionThe Ports Authority’s lump-sum payment, which is the largest component of the $29.8 million

The Ports Authority’s payment is the $26 million recorded as payable to shareholders, less deductions for tax and late payment. The Ports Authority has already paid a value added tax liability of $3.9 million to the Inland Revenue Department and will settle a further $195,000 in late payment. Subtracting both from $26 million gives $21.905 million — the Sunday Times figure exactly.

Add the $7.85 million the project company itself held as distributable cash at the end of 2025, and the total comes to $29.755 million, which is the $29.8 million the Daily FT reports. Every published figure in the settlement ties to every other one.

Only a tenth of the announced investment was ever put in

The gap between the first and second rows of that table is the substance of the story. Against the $392 million announced in April 2023, the partners had contributed $37.1 million in cash by the end of 2025 — about 9.5%. The project was never built.

The contributions were $26 million from Fortune Centre Group Limited (FCGL), China Merchants Port’s wholly owned subsidiary, and $5.6 million each from Access Engineering and the Ports Authority. Those three figures sum to $37.2 million against the $37.1 million total reported; the Daily FT describes the total as approximate, and the difference is rounding.

A further derivation follows from the same figures. If $26 million of the $37.1 million sat with the Ports Authority and $7.85 million remained with the project company, roughly $3.3 million was consumed by the project company over its life. Neither filing states this figure or says what it was spent on.

Who loses what

Both sums will be shared in proportion to shareholdings — 70% to FCGL, 15% each to Access Engineering and the Ports Authority. On that split FCGL receives about $20.8 million and the other two about $4.5 million each.

So FCGL recovers about $5.2 million less than its $26 million contribution, and Access Engineering about $1.1 million less than its $5.6 million. The Ports Authority’s own 15% holding is subject to the same shortfall, while it is simultaneously the party making the $21.905 million payment.

The partners will now move to strike off or wind up the project company, sharing those costs in the same 70:15:15 ratio.

What Sri Lanka had granted

The Sunday Times sets out the terms the project carried, and they were substantial.

The hub was gazetted as a strategic development project in December 2023, granting 15-year exemptions on corporate income tax and on tax on dividends. Sri Lanka had also granted China Merchants Port 50-year sole and exclusive rights to run port-related logistics in the Port of Colombo — barring the Ports Authority from granting any third party the right to carry out port-related logistics or warehousing services there at a rate lower than the royalty fees payable by the project company.

The Sunday Times adds a finding of its own: despite the announcement that the project will not proceed, it found no evidence on the Department of Government Printing’s website that the gazette had been revoked.

The project company was incorporated in the British Virgin Islands, and the building was to be five storeys.

The stated reason

China Merchants Port said it had reassessed the project “in view of changes in external circumstances, including adjustments to the SACLH Project’s implementation environment and timetable as well as the respective commercial considerations of the parties,” concluding that terminating it would be in the best interests of the parties. The wording is identical in both accounts, both quoting the Hong Kong filing.

The company’s board, including its independent non-executive directors, said the settlement terms were normal commercial terms, fair and reasonable, and in the interests of shareholders as a whole.

A disclosure point worth noting

Under Hong Kong’s Listing Rules the Ports Authority counts as a connected person of China Merchants Port at the subsidiary level. The reason is a separate shareholding: the Ports Authority holds 15% of Colombo International Container Terminals, which operates the Port of Colombo’s South Terminal and in which China Merchants Port holds the remaining 85%.

The state landlord of the Port of Colombo is therefore a minority partner of the Chinese operator in the port’s South Terminal, and was a minority partner in the abandoned hub — which is why the settlement required disclosure as a connected transaction in Hong Kong rather than being an ordinary commercial unwinding.

Update, 19 October: the Ports Authority speaks, and will re-tender

The Sri Lankan side has now commented, which was the largest gap in the account above. NewsFirst carried the Ports Authority’s own statement on Monday afternoon, and it is substantially a forward-looking one.

The Authority says it will develop a new logistics hub at the Port of Colombo under a Public-Private Partnership model, with the investor chosen through a competitive bidding process, NewsFirst reported. The facility is to occupy “a substantial land area within the port” and to support a broad range of logistics and value-added services.

The stated ambition is to move Colombo “from primarily a container transshipment port into a fully integrated maritime and logistics hub” serving international supply chains. The Authority says the new approach should attract investment, widen private-sector participation, make better use of port infrastructure and generate sustainable long-term revenue.

On the collapse itself the Authority is firm that it is not a retreat: the decision to discontinue the earlier venture is, it says, an opportunity to pursue a model better aligned with Sri Lanka’s long-term economic and commercial objectives.

One caution on what this does and does not answer. The question posed above was what happens to the SACLH land. The Ports Authority says the new hub will sit on a substantial land area within the port — it does not say it is the same site, and no filing states that it is. The land question is narrowed, not closed.

Lanka Business Online dates the settlement and confirms the arithmetic

Lanka Business Online reported the termination from the same Hong Kong announcement, and supplies the date this article recorded as missing: the company announcement was released on 15 October 2026, and it was on that announcement that FCGL, Access Engineering and the Ports Authority signed the settlement agreement. It names the project company as SACL.

More usefully, it states independently the figure this desk had derived rather than read. LBO reports that the Ports Authority will cover tax and late-payment liabilities to the Inland Revenue Department totalling approximately $4.095 million, leaving $21.905 million which, with the project company’s $7.85 million cash balance, is distributed 70:15:15. It puts FCGL’s share at about $20.83 million and Access Engineering’s and the Ports Authority’s at about $4.46 million each.

Every one of those matches the derivation set out above — $3.9 million of VAT plus $195,000 of late payment is $4.095 million, and the shares were computed here as “about $20.8 million” and “about $4.5 million”. A derivation this desk published from two other outlets’ figures has been confirmed by a third outlet reading the primary filing.

LBO also adds a fact neither earlier account carried: the parties decided to wind the venture up “following consultations with local government authorities”, settling on what it calls a neutral handling approach in which invested capital is refunded and outstanding matters resolved. That places Sri Lankan officialdom inside the decision rather than on the receiving end of it — though no filing says which authorities, or when.

A second figure for the project’s value, and it is not the one above

NewsFirst values the abandoned development at “approximately USD 280 million.” The table above carries $392 million, the figure the Daily FT attributes to the April 2023 announcement.

Both outlets are verified and neither is obviously wrong: the two may be an original announcement value and a later revised scope, or two different measures of the same thing. No filing reconciles them, and this desk is not choosing between them.

The gap matters because of what the figure is used for. Against $392 million the $37.1 million actually contributed is 9.5%; against $280 million it is 13.3%. The conclusion drawn above — that only a small fraction of the announced investment was ever put in — survives either denominator, but the precise fraction depends on which headline figure a reader starts from.

Not reported

Neither account says what the “adjustments to the implementation environment and timetable” actually were, which is the one phrase standing in for the entire cause of the collapse. The consultations with local government authorities that LBO reports are not described, dated or attributed to any named body. Nothing explains what the late payment to the Inland Revenue Department was for.

There is still no comment from the Ministry of Ports, Access Engineering or the Treasury, and no statement on whether the $21.905 million has been budgeted or when within the 30 days it falls due. The Ports Authority’s statement is about the next project, not about the money owed on this one.

Nothing says when the new tender will open, what the new hub is expected to cost, how large “a substantial land area” is, or whether China Merchants Port would be eligible to bid for the replacement. The Sunday Times’ finding that the project’s strategic development gazette appears not to have been revoked remains unaddressed by any later filing.

The $392 million figure is from April 2023 and is the announced project value, not a current one. It is reported here as the scale originally claimed for the project, not as money lost.

Sources: Daily FT, Sunday Times, NewsFirst, Lanka Business Online.