Officials told Parliament’s Committee on Public Accounts (COPA) that about Rs 1,664 million has been spent on 72 education development projects launched between 2018 and 2021, and that 20 of them are stalled over contract issues, the Daily Mirror, Hiru News and Parliament reported on Saturday (21 November).
The committee met on 19 November under MP Kabir Hashim. It was examining the Education Ministry’s tri-annual reports for 2021 to 2023, the Auditor General’s 2024 report and the ministry’s current performance.
The 72 projects
Of the 72 projects, 35 are complete and 13 are ongoing. Four have been suspended and 20 are stalled over contractual issues. Officials said steps were being taken to resolve the contract problems and restart the stalled work.
The Daily Mirror’s headline calls all 72 projects stalled and Parliament’s release headline calls them abandoned. The figures in the text of all three reports are those above.
Other points raised
- National Schools programme: Nearly Rs 1,600 million was allocated in 2019 to develop selected schools and buy equipment under a plan for three National Schools in each Divisional Secretariat Division. A policy decision was later taken not to continue it, and the committee asked for a report on the funds allocated to each school and the work done.
- Computers: A stock of computers ordered by the ministry was rejected because it did not meet the technical specifications. No payments were made, and the supplier has filed two court cases.
- NEMIS: Priority has gone to entering teacher information and student assessment data into the National Education Management Information System. Teacher transfers in several provinces already run through it, and officials plan to extend it to all provinces and National Schools.
- Delays: Officials said late estimates, a shortage of technical officers and tender problems had affected the use of capital allocations. The committee also raised slow replies to audit queries.
Deputy Ministers Nalin Hewage and Aruna Jayasekara, a retired Major General, and several MPs attended.
Not reported
None of the reports names the projects, says which are stalled, gives their value or says when work is due to restart. They do not split the Rs 1,664 million by project status, name the computer supplier or value the rejected order.