Sri Lanka’s mega development projects had spent only Rs 96.8 billion, or 15.3%, of their Rs 632.4 billion allocation for 2026 by the end of June, according to a Finance Ministry review.

The quarterly report by the Finance Ministry’s Department of Project Management and Monitoring (DPMM) covers 210 projects that each cost more than Rs 1 billion, Daily FT reported on Monday. Spending reached 39.3% of the first-half target of Rs 246.21 billion. The Sunday Times carried the same findings on 22 November.

The department said money was not the problem. “Although there was no delay in the release of funds from the General Treasury, financial utilisation remains low due to project activities not being implemented as expected,” the report said, as quoted by Daily FT. Unpaid bills stood at Rs 12.5 billion.

Spending by funding source

Delays

Of 47 projects due to finish by end-June, only 10 did, and 20 made no physical progress during the quarter. The review rated 32 projects critical and 39 as needing special attention.

The China-funded Section 1 of the Central Expressway spent Rs 2.88 billion of its Rs 64.15 billion allocation, about 4.5%. It is 50.5% complete, and its deadline has moved from September 2024 to September 2028, Daily FT said.

Contractor performance was the most common cause of delay (28 projects), followed by procurement (22), third-party approvals (20) and shortages of project management staff (12). The report also cited fuel supply limits, higher fuel prices and difficulty obtaining bitumen.

Budget context

Daily FT linked the findings to Budget 2027, presented on 12 November, which lifts capital spending by 35% to Rs 2 trillion. Treasury data show capital expenditure and net lending of Rs 276.6 billion in the first half, 16.1% of the Rs 1.72 trillion annual estimate. The Government has already moved procurement earlier to try to spend the larger budget.

The 210 projects have a combined estimated cost of Rs 3.7 trillion, and a further Rs 1.8 trillion is needed to complete them.