Cabinet awards Rs. 1.07 billion to widen 4.76 km of the Kandy-Jaffna road
Tudawe Brothers won the A009 contract as lowest responsive bidder out of eight. The per-kilometre rate is close to three times what Cabinet approved for.
Tudawe Brothers won the A009 contract as lowest responsive bidder out of eight. The per-kilometre rate is close to three times what Cabinet approved for.
The commission has recorded evidence from more than 70 people and expects to finish next week. Its current term ends on October 16.
Anura Karunathilake put the loss at Rs. 15.765 billion and said Rs. 16.989 billion in penalties and performance bonds has been withheld from suppliers.
Cabinet approves wastewater contract for Eravurpattu zone; China firm wins tender.
Five companies win road rehabilitation contracts; traffic study awarded for Colombo.
Cabinet approved Phase III of the Baseline Road Extension Project — 0.86km from Kirulapone to Dutugemunu Street, widened to six lanes with an underpass.
Wasantha Mudalige says the TOR for a 500-camera police procurement carries unedited AI output, and that bids ranged from Rs. 50 million to Rs. 360 million.
CBSL has called for expressions of interest in an enterprise data system to strengthen its data management and analytics, with a 26 October deadline.
Three Rural Ways packages in Kalutara, Kilinochchi and Mullaitivu all went to RR Construction, the lowest responsive bidder out of 17 bids submitted.
German firm Muhlbauer ID Services won the tender for pre-printed NIC blanks after eight international bids, on a proposal from President Dissanayake.
China Petroleum Pipeline Engineering wins $40.84m contract to build 92,000 m³ jet fuel tank farm and pipeline to BIA, two years after Cabinet approval.
The GMOF says wound-dressing and orthopaedic supplies have run short at Colombo National Hospital, with patients sent to outside pharmacies.
Cabinet awards SITA Switzerland SARL a US$4.01mn five-year contract for SriLankan Airlines' global network. Only one bid was received.
The retired air chief reported to the Financial Crimes Investigation Division at 9.30am over the long-running MiG aircraft transaction inquiry.
Audit finds sulphur and ash limits relaxed on 2015 coal contract without Cabinet approval.
CIABOC arrested the former minister as he arrived to give a statement. Only NewsFirst gives the allegation: a Rs. 7.97mn loss on Polgolla auditorium chairs.
The former minister and Design Point owner Hemantha Lalith de Silva were bailed on Rs. 2.5mn sureties with a travel ban. CIABOC had sought remand.
Authorities to pay full price for immunisation programme after reclassification as upper-middle income.
Dr. Chamal Sanjeewa alleges a tug-of-war between officials and specialists has held up linear accelerators funded by the ADB and the Treasury.
Coal tender documents used estimates instead of actual plant requirements, audit officer tells Presidential Commission.
Ex-Fisheries Corporation chairman arrested by CIABOC, remanded after failing to meet bail conditions.
Cabinet has awarded contracts for 2.28 million tonnes of Norochcholai coal, long-term petrol, diesel and crude supplies, and three new Muthurajawela tanks.
The Public Security Minister said a fresh procurement process has begun for the PKI security system after the earlier tender was cancelled over shortcomings.
The former state minister alleged bid documents were issued a day after a supplier finished registering, and questioned the rejection of Lakvijaya lab reports.