The 2027 Budget proposes installing synchronous condensers at New Habarana and Mannar and a STATCOM facility at the Padukka grid substation, to keep the national electricity system stable as renewable generation takes a larger share of supply.
President Anura Kumara Dissanayake announced the projects in Thursday’s Budget speech, Hiru News reported, presenting them as a response to the stability problem that arises when a high proportion of renewable energy joins the grid.
What is being installed
- Two synchronous condensers of 75 MVA each at New Habarana
- Two synchronous condensers of 75 MVA each at Mannar
- A 300 MVAr STATCOM facility at the Padukka 220 kV grid substation
Both technologies address the same underlying issue. Wind and solar generators connect to the grid through power electronics and, unlike conventional thermal and hydro plant, contribute little of the rotating mass and reactive power that hold system voltage and frequency steady. Synchronous condensers restore some of that rotating inertia; a STATCOM provides fast reactive power support electronically.
The siting is consistent with where Sri Lanka’s renewable build-out is concentrated — Mannar is the centre of the country’s wind development.
Financing and timeline
The President said the project is financed with World Bank assistance and is expected to start in 2027 and finish in 2029.
The measures sit alongside the separate transmission expansion work already under way, including the Sampur–Kappalthurai transmission contract awarded on 3 November.
Update, 17 November: the sector plan around the equipment
A fuller account of the Budget’s electricity proposals, published by The Island on 17 November under the byline of Ifham Nizam, places the condensers and the STATCOM inside a Rs 26.5 billion grid-strengthening investment — the figure this desk reported separately in the solar battery subsidy proposals. That answers part of the cost question left open below.
The filing adds several elements absent from the original account:
- Why now. President Dissanayake cited the nationwide power system failures of February 2025 and October 2026 as having exposed the need to strengthen system protection, frequency control, power flow management and network protection.
- The renewable share. About 62 percent of installed generation capacity is currently renewable, with a target of 69 percent by 2029. The grid-stability spending is presented as the enabling condition for that increase rather than as generation investment in itself.
- A Wide Area Monitoring System, under a World Bank technical assistance programme, to identify unstable network conditions in advance.
- Battery storage trajectory. Storage connected to the national system is projected to rise from 160 MW in 2026 to 560 MW in 2027, with a longer-term target of 1,245 MW by 2029.
- A 30 MW battery facility at the Norochcholai Lakvijaya coal complex, to supply supplementary power during emergencies. The 900 MW plant is the single largest element of the supply system.
- Private investment to be invited for two 220 kV transmission lines — Norochcholai to Wariyapola, and Moneragala to Hambantota — and for the New Habarana–Kirindiwela 400 kV line.
Sourcing note
The original report rested on a single verified newsroom: no Daily Mirror, NewsFirst or EconomyNext filing covered the grid-stability proposals at the time of writing, and the Daily Mirror’s sector-by-sector Budget breakdown listed no grid transmission line. The Island’s 17 November account is a second verified source for the same Budget speech, filed five days after it.
Not reported
The Rs 26.5 billion covers grid strengthening as a whole; neither filing breaks out the cost of the condensers and STATCOM specifically, names an implementing agency, or says whether the equipment is to be procured as one package. Neither gives a figure for the private investment sought on the three transmission lines, or a timetable for inviting it.